Sector 25 is to the north of Residencial Bella Vista, Residencial Vista Sal and Residencial Salinas Beach. It borders the N-332, the Avenida Asociación Víctimas del Terrorismo and Calle's César Mateo and Cecilio Gallego. Located in front of the new headquarters of the real estate company TM Group in La Hoya and the International Auditorium.
https://www.informacion.es/vega-baja/20 ... 78912.html
Google translate, minus video and images:
The renovation of the Sector 25 park in Torrevieja: three months stopped because the City Council lacked the roads permit
The project, valued at more than 5 million euros, includes pedestrian itineraries in easement areas of the N-332 and the works began without being communicated to the Ministry, but they have already received the go-ahead, according to the PP government team
The renovation works of the Sector 25 park of Torrevieja they have been paralyzed for more than three months because the City Council started them without the permission of the Ministry of Transport, the administration that manages the variant of the N-332 that marks the green zone, according to the answer offered by the councilor of the area, Concha Sala, to a question of the ordinary plenary session on Monday made by councilor spokesperson of Sueña Torrevieja, Pablo Samper, on the delay of the project.
Clarifications in the plenary session
Samper asked the councilor to clarify what work has been executed, if there are delays and if the planned completion period is maintained. The works were to begin in November 2025, they did so in December, with an execution period of 12 months. Months after that date, the visible advances "are limited to earthworks and the occasional presence of machinery", in addition to all the fencing, according to the same formation. Samper recalled that the neighbors "have been waiting for years for this action to really advance." According to the mayor, "the reality on the ground is that hardly any progress is observed." The municipal group considers it necessary for the City Council to explain the real situation of the work.
Announce projects
"It is not enough to announce projects; they must be executed, deadlines must be met and explanations must be given when the works are not progressing at the planned pace," says Samper and maintains that it is a green area "highly anticipated by residents" and that the action must improve the environment. "It cannot remain in another announcement without monitoring or transparency," he adds.
Sala explained that the works of the new green area of Sector 25 are pending to receive favorable notification from Highways in order to continue. He assured that the city council initially processed a communication to Roads following the indications of the municipal technician. The Ministry later decided that the works could not "simply communicate" and that they needed express authorization. This requirement has caused the work to be stopped. The municipal technicians and the drafters of the project have maintained contacts with the Demarcation of Roads to adjust the action. The objective, he said, is to make the easement area and the perimeter pedestrian flows that are contemplated in the project compatible within those easement areas.
Sala defended that this technical exchange seeks to guarantee that the state infrastructure and the new green area "coexist without interference in the future". The mayor said that the City Council has already known for days that the resolution is favorable and that only the notification needs to be received. "The work will continue shortly," he said.
Regarding the completion deadline, Sala explained that the stoppage time will be automatically added to the work's schedule. According to his calculations, if the initial deadline ended in December 2026, the completion could be moved by about three months, although the City Council will try to make it less.
Presentation
Mayor Eduardo Dolón, the councilor herself and those responsible for the work, the company Actua (Hozono Group) announced the start of this project at the end of last October at a press conference. The action includes morethan 700 trees, 95 palm trees, 70,000 square meters of surface area and 5.4 million euros (VAT included) of investment, of which they even gave a start date: November 11 of that year although it was later delayed to the end of December. A renewal that comes after the demand of the neighbourhood in the face of the abandonment and degradation of what should be, for fifteen years, the main green area of Sector 25. The developers of this extensive residential area of Torrevieja, which soldthe urban plots where the City Council also authorized all the major building licenses for thousands of homes to be built, did not manage to build the park. The investment is part of the park and garden maintenance contract itself - valued at 113 million - which in one of its lots provides for the rehabilitation and development of green areas to be carried out by Actúa.
Torrevieja Sector 25 Park Renovation Completion Date Delayed
Advertisement
Create an account or sign in to join the discussion
You need to be a member in order to post a reply
Create an account
Not a member? register to join our community
Members can start their own topics & subscribe to topics
It’s free and only takes a minute


¡SHARE TOPIC!